Written by Shauna Weatherly, President of FedSubK, SME advisor to GovPort. Original post found here.
Often small businesses face several conundrums when they are on the receiving end of a notice of elimination from the competitive range and then faced with a decision on when to receive a debriefing or, if necessary, to protest. From the inside, as a Contracting Officer, I didn’t ever fully understand the concern over taking a debriefing and contemplating a protest. I worried about getting a protest because it can derail a contract for months, but I never understood the concern from the side of the business.
Before getting into what I’ve learned since becoming a consultant, let’s talk about debriefings a little bit. If you’ve never been through the debriefing process, or even if you have but haven’t felt you’ve received the information you needed, here Is a run-down of why asking for the debriefing at any stage of the process (pre-award elimination or post-award) is a good thing.
The RFP will state when the Government plans to establish a competitive range for the purposes of a more efficient evaluation. A competitive range determination and pre award notification of exclusion of the proposal from further consideration is made when the Government believes that there is a clear delineation between proposals that have a chance of receiving contract award and those that don’t. When this determination is made, it is done so a few reasons:
The notification will offer the opportunity to request a debriefing within 3 calendar days of receipt of the notice. Or you may opt to take a post award debriefing instead. If you don’t make this request in a timely manner, the Government is not required to provide a debriefing (pre or post award).
A debriefing is where you can find out how the Government viewed your proposal and find out how to improve on that perception for the next time you propose to that agency or another.
Should I ask for a debriefing?
The answer here is always going to be YES. Even if you receive a written debriefing abstract with your notification letter, ask to talk to the Contracting Officer via a debriefing request. The question is when.
It depends. A few things to consider are:
A post award debriefing provides information that is beneficial to seeing the competition landscape for the contract. At a minimum, the post award debriefing includes:
You can see that it’s significantly more info. Waiting for it and then protesting exclusion from the competitive range on grounds of something you knew at the time of exclusion will most likely render your protest untimely.
Under no circumstances will debriefings include:
This is more complicated, based on things I’ve learned since becoming a consultant. There is a perception that if a business protests, a CO/KO or agency might hold a grudge. It doesn’t happen (I know, I’ve never seen it in over 35+ years). But there is a real fear among small businesses that a protest isn’t worth the risk of being labeled as a troublemaker or ruining an existing relationship with an agency or its personnel.
Example in point, last year a client of mine received notice they had been eliminated from the competitive range. In the notice, the CO/KO provided its rationale for removal. The client requested a pre-award debriefing from the CO/KO the same day. The client was interested in the other two pieces of info that, at a minimum, they were entitled to under FAR 15.505(e) as part of a pre-award debriefing:
The CO/KO's response to the client’s request was that the request for a preaward debriefing was noted but that they had not made an award and were still in source selection. Well, duh! So, now what? That’s not very compelling.
The client sent a follow up outlining that:
The response the client received from the agency? Crickets. Even with follow up emails every two weeks.
Four months later, after award had been made, the agency provided a letter and attachment titled "Preaward Debriefing" AND the info provided was limited to what was allowed under FAR 15.505(e) for a pre-award debriefing. Disappointing at best.
Did the client have a legitimate complaint? Likely. Particularly because the debriefing disclosed a measure used by the agency that was not disclosed in the RFP evaluation criteria and was indicated as part of the basis for its elimination.
Did the client do anything about it? It thought about it but wrestled with how a complaint or protest might impact their current work relationships on other projects with the same CO/KO as well as future opportunities. The client ultimately made a business decision to preserve the existing business relationship, accept the debriefing provided, and move on. And this happens more often than you'd think.
You should walk away with and understanding of places in your proposal where you missed the mark and can improve your next proposal, even when not with the same agency. Capturing debriefing feedback is important and doing your own "hot wash" after a debriefing is even more important. Don't make the same mistakes twice! Update your proposal team review checklists with your findings after each debrief.
While you may weigh existing work with the same agency, existing relationships, etc., in the matter of the timing of your request (and potential protest), know that from the CO/KO perspective inside, they don't take debriefing requests and protests personally. They aren't allowed to view your business less favorably on future proposals.
What's happens next depends on YOU. Only YOU can determine the best time to request a debriefing when eliminated from the competitive range, particularly if there is the potential of a protestable issue. And only YOU can mitigate proposal writing mistakes from occurring again and improve your proposal writing and review processes. And learning from those mistakes should be an expected part of the proposal life cycle on our way to that winning proposal.